Lowes Hardware, Monroe

General Contractor: Robinson Construction

  

   Progress has been swift over the last weeks and the interior slab is over half way poured.  Today's pour began at 2:00 a.m. and made use of two laser screeds to help put down concrete nearly faster than the trucks could supply it. 

   Two laser screeds were used at the same time to help speed up the pour.

   Work continues on the exterior details, with the first slab pour not far away.

The concrete work on the loading bay is now finished.

Exterior details have been completed in the front and back of the building.

  

   Work has progressed well with the footings nearly poured and the walls going up quickly.

   The concrete work for loading bay has been completed.

   Excavation for the footings has almost been completed and the first pour of the job is in place.

The first footing is in place and ready for walls.

   The initial site has been leveled and is ready for excavation of the footings.