Army Growth Project-Jackson Avenue, UEPH, Fort Lewis This project consists of foundation and slab work for a barracks complex.
The weather turned out great for the second slab pour of the project.
The power trowels were busy putting the finish on the lower section of the pour, and on the upper section the slab is all but done.
An excellent finish to a good day's pour.
With the framers hard at work on the previously poured section of slab, crews carry out excavation work in preparation for the next section.
The plumbers and electricians will place their fittings before the next building is readied for it's slab.
The first slab pour of the project went well with the weather holding out all day.
A considerable amount of dirt work will take place before the next buildings are ready for slab pours.
|